Expansion and integration of Terminal Building No. 2 with Terminal Building No. 3 at the San Jose del Cabo International Airport in Baja California Sur.

The remodelation is built in 3 stages:

1st Stage: The frontage and floor will be remodeled, columns will be reinforced, and walls and finishes will be added.

2nd Stage: The foundations and footings for the jet bridges towers will be made;

3rd Stage: The dismantling of ramps and the construction of the jet bridges are carried out.

The main challenge in the execution of this construction is the interaction with the usual activities of the airport, since it is not possible to interfere with its daily operations. The area in which the complexity of coordination is greater is in the so-called "air side" (air traffic zone), due to the schedules and normative regulations of the airport operations, the early planning of activities along with the early request for permits to release the necessary areas, are of greater importance.

 

Sun, 07/01/2018 - 08:00

ENGINEER’S DAY

Wed, 05/16/2018 - 13:30

BIM

Tue, 08/15/2017 - 20:15

VALUE ENGINEERING IN CONSTRUCTION

Carretera Transpeninsular Km 43.5, 23420 San José del Cabo, B.C.S.
Latest Projects